| (1)Cleaning
the floor |
(2)
Confirming one level, making position line |
(3)
Dipping the tiles into clear water for 1 hour |
| |
|
|
| |
|
|
| (4)
Picking up the tiles, applying 1:2 cement paste (
or 1:0.15 cement and lime cream) onto the binding
surface of the tiles, then constructing onto the floor |
(5)
Pressing the floor tiles with wooden hammer, preventing
hollow |
(6)
Making sure the tiles are of the same level |
| |
|
|
| (7)
After constructing, it is better to deepen the cement
in the gap, removing dirts from the tile surface |
(8)
Feeding tile gap after it is a bit dry |
(9)
Completely cleaning the tiles surface |
| |
(10) Cleaning
the stubborn dirt with oxalic acid or hydrochloric
acid.
|
|